Cost overruns and delays in infrastructure projects: the case of Stuttgart 21

Steininger, Bertram I. (författare)
KTH,Fastighetsekonomi och finans
Groth, Martin (författare)
RWTH Aachen University, Aachen, Germany
Weber, Birgitte (författare)
RWTH Aachen University, Aachen, Germany
 (creator_code:org_t)
Emerald, 2021
2021
Engelska.
Ingår i: Journal of Property Investment & Finance. - : Emerald. - 1463-578X .- 1470-2002. ; 39:3, s. 256-282
  • Tidskriftsartikel (refereegranskat)
Abstract Ämnesord
Stäng  
  • Purpose: We investigate causes for the cost overrun and delay of the railway project Stuttgart 21. Besides, we try to forecast the actual costs and completion date at an early stage. Design/methodology/approach: The results of exploratory research show the causes for the cost overrun and delay of Stuttgart 21; we compare our findings with other railway projects. To estimate the costs at an early stage, the reference class forecasting (RCF) model is applied; to estimate the time, we apply an OLS regression. Findings: We find that the following causes are relevant for the cost overrun and delay of Stuttgart 21: scope changes, geological conditions, high risk-taking propensity, extended implementation, price overshoot, conflict of interests and lack of citizens' participation. The current estimated costs are within our 95% confidence interval based on RCF; our time forecast underestimates or substantially overestimates the duration actually required. Research limitations/implications: A limitation of our approach is the low number of comparable projects which are available. Practical implications: The use of hyperbolic function or stepwise exponential discount function can help to give a clearer picture of the costs and benefits. The straightforward use of the RFC for costs and OLS for time should motivate more decision-makers to estimate the actual costs and time which are necessary in the light of the rising demand for democratic participation amongst citizens. Social implications: More realistic estimates can help to reduce the significant distortion at the beginning of infrastructure projects. Originality/value: We are among the first who use the RCF to estimate the costs in Germany. Furthermore, the hyperbolic discounting function is added as a further theoretical explanation for cost underestimation.

Ämnesord

SAMHÄLLSVETENSKAP  -- Ekonomi och näringsliv (hsv//swe)
SOCIAL SCIENCES  -- Economics and Business (hsv//eng)

Nyckelord

cost overrun
time overrun
infrastructure
reference class forecasting
hyperbolic discounting
principal-agent theory
Nationalekonomi
Economics
Planering och beslutsanalys
Planning and Decision Analysis
Urban and Regional Studies
Urbana och regionala studier
Fastigheter och byggande
Real Estate and Construction Management

Publikations- och innehållstyp

ref (ämneskategori)
art (ämneskategori)

Hitta via bibliotek

Till lärosätets databas

Hitta mer i SwePub

Av författaren/redakt...
Steininger, Bert ...
Groth, Martin
Weber, Birgitte
Om ämnet
SAMHÄLLSVETENSKAP
SAMHÄLLSVETENSKA ...
och Ekonomi och näri ...
Artiklar i publikationen
Journal of Prope ...
Av lärosätet
Kungliga Tekniska Högskolan

Sök utanför SwePub

Kungliga biblioteket hanterar dina personuppgifter i enlighet med EU:s dataskyddsförordning (2018), GDPR. Läs mer om hur det funkar här.
Så här hanterar KB dina uppgifter vid användning av denna tjänst.

 
pil uppåt Stäng

Kopiera och spara länken för att återkomma till aktuell vy