1. |
- Steininger, Bertram I., et al.
(författare)
-
Cost overruns and delays in infrastructure projects: the case of Stuttgart 21
- 2021
-
Ingår i: Journal of Property Investment & Finance. - : Emerald. - 1463-578X .- 1470-2002. ; 39:3, s. 256-282
-
Tidskriftsartikel (refereegranskat)abstract
- Purpose: We investigate causes for the cost overrun and delay of the railway project Stuttgart 21. Besides, we try to forecast the actual costs and completion date at an early stage. Design/methodology/approach: The results of exploratory research show the causes for the cost overrun and delay of Stuttgart 21; we compare our findings with other railway projects. To estimate the costs at an early stage, the reference class forecasting (RCF) model is applied; to estimate the time, we apply an OLS regression. Findings: We find that the following causes are relevant for the cost overrun and delay of Stuttgart 21: scope changes, geological conditions, high risk-taking propensity, extended implementation, price overshoot, conflict of interests and lack of citizens' participation. The current estimated costs are within our 95% confidence interval based on RCF; our time forecast underestimates or substantially overestimates the duration actually required. Research limitations/implications: A limitation of our approach is the low number of comparable projects which are available. Practical implications: The use of hyperbolic function or stepwise exponential discount function can help to give a clearer picture of the costs and benefits. The straightforward use of the RFC for costs and OLS for time should motivate more decision-makers to estimate the actual costs and time which are necessary in the light of the rising demand for democratic participation amongst citizens. Social implications: More realistic estimates can help to reduce the significant distortion at the beginning of infrastructure projects. Originality/value: We are among the first who use the RCF to estimate the costs in Germany. Furthermore, the hyperbolic discounting function is added as a further theoretical explanation for cost underestimation.
|
|