Economic lot scheduling problems incorporating a cost of using the production facility
-
Brander, Pär (författare)
-
- Segerstedt, Anders (författare)
- Luleå tekniska universitet,Industriell Ekonomi
-
(creator_code:org_t)
- 2010-10-11
- 2009
- Engelska.
-
Ingår i: International Journal of Production Research. - : Informa UK Limited. - 0020-7543 .- 1366-588X. ; 47:13, s. 3611-3624
- Relaterad länk:
-
https://urn.kb.se/re...
-
visa fler...
-
https://doi.org/10.1...
-
visa färre...
Abstract
Ämnesord
Stäng
- This paper considers scheduling the production of several different items on a single machine with constrained capacity, commonly known as the Economic Lot Scheduling Problem (ELSP). Most traditional approaches for the ELSP consider the sum of the setup cost and inventory holding cost and provide cyclic schedules that minimize this sum. In practice, there are not only costs for setups and inventory holding, but also costs for operating the production facility due to e.g. electricity, service, maintenance, tools, operators etc, which depend on the number of hours the facility is operating per working day. In this paper, we modify the traditional cost function to include not only setup and inventory holding cost but also a time variable cost for operating the production facility. The paper shows it is possible to adapt a previous heuristic procedure to this complemented cost. The model can help to determine cyclic schedules and the number of production hours per working day.
Ämnesord
- TEKNIK OCH TEKNOLOGIER -- Maskinteknik -- Produktionsteknik, arbetsvetenskap och ergonomi (hsv//swe)
- ENGINEERING AND TECHNOLOGY -- Mechanical Engineering -- Production Engineering, Human Work Science and Ergonomics (hsv//eng)